From Palm Oil Mill Effluent to Compressed Biomethane: The Process Chain

by | Jan 7, 2026 | Biogas from POME

From Palm Oil Mill Effluent to Compressed Biomethane: The Process Chain

Upgrading biogas from palm oil mill effluent to compressed biomethane (CBM) takes five steps after the digester: remove hydrogen sulphide, dry, compress, strip CO₂ and compress again for vehicles. This post describes the chain proposed for a 60 tonnes per hour mill, in which a covered lagoon supplies both the fuel for vehicles and the power for the plant.

The challenge: vehicle-grade gas from a wet, sour source

The mill’s effluent flow was about 840 m³/day at 80,000 mg/l COD, or roughly 54 tonnes of COD a day. A covered lagoon would produce around 43,000 Nm³/day of biogas at 60 to 70% methane. The gas has to meet European standards for biomethane as a transport fuel (EN 16723-1) and gas quality (EN 16726), and be compressed to 250 bar for dispensing. The plant’s own load, under 500 kW, would be met by a gas engine on the same biogas.

The approach: stage by stage

StageDutyDesign figure
Biological scrubberBulk H₂S removal5,000 ppm in, 300 ppm out; two vessels
DewateringDry the gasDew point about 4°C
BoosterMove gas through the plant300 mbar, duty and standby
Compression and coolingRaise pressure for clean-upWith re-heating of the gas
Activated carbon polishingH₂S polishing200 ppm in, 1 ppm out; four vessels
Low-temperature coolingPrepare gas for CO₂ removalAbout -25°C
Pressure swing adsorptionRemove CO₂Controls CO₂ in the product
High-pressure compression and dispensingFill vehicles250 bar

The flare has more than one job

The PSA exhaust still contains methane and cannot be vented. The flare burns it, together with off-specification gas and surplus, up to 1,500 Nm³/h. It doubles as an emergency flare.

Cooling the feed

Lagoon feed is best at 35 to 40°C, so a POME cooler is included, either an open air-to-effluent type or an enclosed system.

Why the design is a partnership

The proposal combined the lagoon and gas train with specialist upgrading and dispensing equipment from a partner, plus local civil works. Boundaries were the effluent inlet, the effluent spill-point and the dispensing station. A key assumption is that the refuelling station sits near the plant, otherwise a methane pipeline adds cost.

What to consider for your own project

  1. Treat H₂S in two stages. The biological stage is cheap and the carbon stage guarantees the final figure.
  2. Plan for the off-gas. Methane in a PSA exhaust must be burned.
  3. Locate the dispenser sensibly relative to the plant.
  4. Power the plant from biogas and size the engine for the site load.
  5. Confirm the gas standard that applies in your market.

For UK background, see the government’s Anaerobic Digestion Strategy and Action Plan.

FAQ

What is compressed biomethane?

Biogas upgraded to natural-gas quality and compressed for use as a vehicle fuel.

Why is the gas cooled to -25°C?

To condition it before CO₂ removal.

Why two H₂S stages?

Carbon alone would be used up quickly on raw gas.

How long does delivery take?

About 10 months from order, subject to the rainy season.

Planning a biomethane project?

Contact us with your effluent flow and COD.

Start your enquiry :


Translate »
organics.co.uk

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.