A packaged landfill gas flare with a blower puts the gas-moving equipment, the safety valves and the flare on one skid, so a site with no existing gas-handling equipment can connect its gas main and start burning. In a proposal for a 3,000 Nm³/h landfill in North Africa, a single centrifugal blower pulled gas from the field at -100 to -80 mbar g, lifted it by about 150 mbar, and fed an enclosed flare at 30 to 50 mbar g, holding at least 1,000°C with at least 0.3 seconds of residence.
The challenge: a new landfill gas system with nothing in place
The landfill had no suitable gas-moving equipment. The packaged “SC/P” scope was designed for exactly that case: a skid carrying a blower and its protection, connected to an SC range ground flare stack. The design conditions were:
| Parameter | Value | What it means |
|---|---|---|
| Maximum gas flow | 3,000 Nm³/h | About 18 MW of thermal duty at the design point |
| Minimum gas flow | 600 Nm³/h | A 5:1 turndown |
| Methane | 25% to 60% | The flare must cope with a weak gas as the site ages |
| Oxygen | 0% to 5% | Air drawn in with the gas |
| Inlet gas | About 20°C, saturated | Moisture must be removed ahead of the blower |
| Suction at the plant inlet | -100 to -80 mbar g | Set by the extraction system |
| Blower head | About 150 mbar g | Enough to push gas through the flare train |
| Supply pressure to the flare | 30 to 50 mbar g | What the burner needs |
The approach: the skid in the order the gas meets it
1. Inlet and knockout pot
Gas enters through an inlet butterfly valve to a condensate knockout pot. The pot has a polypropylene mesh filter that removes droplets. The pressure drop across the clean demister is below 3 mbar, and it removes 99% of particles larger than 6 microns. A valved 1-inch drain connects to the client’s drainage.
2. The blower
A single centrifugal gas blower is driven directly by a high-efficiency Ex n rated motor, with a carbon gas seal on the fan housing. Stainless steel bellows and flexible joints isolate it from the pipework. A variable speed drive is controlled by a pressure transmitter on the blower outlet, so the delivery pressure follows a user-chosen set point. This is what lets the same blower serve a falling gas flow as the landfill ages.
An option was offered for a higher-pressure blower with a 300 mbar differential, suitable for feeding most gas engines. We cover how that duty is sized in sizing the gas booster for a ground flare.
3. Protection between blower and flare
- ATEX-compliant flame arresters (EN 12874) on the blower inlet and on the flare inlet.
- A low-pressure switch to indicate line blockage or blower failure.
- A pneumatically actuated main gas safety shut-off valve, which fails closed, with a dedicated compressor.
- A local emergency stop on the skid.
4. The flare
The SC range ground flare has automatic flame temperature control through a PID controller and air louvres. It burns at 1,000°C minimum when methane is above 25%, and cooler at weaker gas. The shroud is lined with 100 mm of ceramic block. Ignition is automatic, with a pilot line, igniters, a UV flame sensor and a secondary air damper whose position is set at commissioning and then controlled by the PID loop. Four DN125 sampling ports sit at 90 degrees around the stack near the top, with an access platform and ladder.
5. Instruments and controls
The standard supply includes vacuum gauges before and after the knockout pot, a PT100 temperature transmitter and a pressure transmitter on the blower outlet, a pitot or anemometer insertion point on the inlet line, a combustion chamber temperature read-out and an orifice plate flow meter. The weatherproof (IP56) control panel holds the PLC, the blower drive, an HMI, and an hours-run clock for the blower. Options were an online gas analyser (methane, carbon dioxide and oxygen) and a data logger. The proposal also listed a wear-and-tear kit (UV bulb, ignition electrode, thermocouples) and an essential kit (ignition transformer, burner control unit, pressure switch) recommended for two years of operation.
Why it works, and the trade-offs
The flare is designed to meet TA Luft emission standards and the European standard for biogas flares, BS EN ISO 22580:2021. Skid mounting means the unit can be tested in the factory before shipping. The flare base and ancillary equipment arrive as one skid, and the upper section of the stack is fitted on site, so installation is mostly connections and erection. In the UK, the Environment Agency’s LFTGN05 monitoring guidance is the reference for enclosed flare temperatures.
What the package does not include matters as much. The exclusions covered foundations and civil works, offloading and installation, gas piping and electrical connections to the flare, dewatering of the gas stream before the plant (the system is not designed to take liquid), condensate management, earthing and lightning protection, third-party inspection, safety integrity level analysis and DSEAR, and flue gas analysis. The scope also made the point that the price included delivery to the port and commissioning by an engineer, but not import duties or delivery to site.
What to consider for your own project
- Check where you need a blower. If gas does not reach the flare at the pressure it needs, a skid with a blower removes the need for separate gas-moving equipment.
- State suction and delivery pressures. The blower head is the difference you need to make up, and the required supply pressure depends on the burner.
- Plan for the long tail. A 5:1 turndown and a 25% methane limit give headroom as the gas weakens.
- Keep liquid out. Provide separate dewatering or a good drainage route from the knockout pot.
- Read the exclusions. Civil works, power and gas connections are all yours.
FAQ
Why does a flare need a blower?
If the landfill’s extraction system does not deliver gas at enough pressure, a blower lifts it to the 30 to 50 mbar g the flare burner needs.
What does the variable speed drive do?
It adjusts the blower speed to hold a chosen outlet pressure, so the skid copes with changing gas flow.
Why is there a knockout pot ahead of the blower?
Landfill gas is saturated. The pot removes droplets and condensate before they reach the blower.
How long does installation take?
The proposals for similar skids described one to two days for erection, set-up and commissioning when the slab, power and gas connections are ready.