Landfill Gas Flare Hire or Buy? Weighing Up a 1,000 m³/h Unit

by | May 15, 2026 | Landfill gas

Landfill Gas Flare Hire or Buy? Weighing Up a 1,000 m³/h Unit

Hiring a landfill gas flare makes sense for a defined short-term need; buying, or a lease purchase, makes sense once you are sure you will keep the unit. This post uses a 1,000 m³/h ground flare hired to a UK waste operator for a landfill site to explain the structure of a hire deal, the accounting catch that surprises many buyers, and what a minimum-specification hire flare contains.

The challenge: a temporary flare that might become permanent

The operator needed a flare quickly for one landfill and was unsure how long it would be needed. Hiring avoids a capital commitment, but the supplier pointed out a problem with the “hire now, buy later” idea.

The approach: three ways to pay

Hire

A weekly rate applied, stepping down after six months and again after twelve. A minimum hire period of six months was guaranteed by the customer, and delivery, installation, commissioning, decommissioning and removal were charged separately. A similar hire of a 1,000 m³/h flare at another landfill used a minimum six-month term with separate charges for installation, delivery and crane hire.

Purchase after hire

The supplier explained why hire payments cannot simply be credited against a later purchase. A hired unit stays on the supplier’s books as an asset and is depreciated over five or seven years, so after six months it is still worth about 90% of its original value. Offsetting hire fees against the price would force the supplier to record a loss on the transaction. A later purchase price is therefore quoted against the depreciated book value, and it falls as the hire period lengthens, but hire fees are not credited.

Lease purchase

The practical alternative is to treat the deal as a sale with staged payments. That means committing to purchase at the start, but paying over time, usually through a lease-purchase arrangement. In this case a lease purchase over a period chosen by the customer could be arranged.

RouteBest whenCatch
HireThe need is short or uncertainHire fees are not credited to a later purchase
Hire, then buyYou expect to keep it but want to waitPrice is set against depreciated value
Lease purchaseYou are confident you will keep the unitYou commit to buy at the start

What a hire flare contains

The unit was a standard 1,000°C enclosed ground flare with a minimum 0.3 second residence time, built on a galvanised skid. It was described as an in-house, minimum-scope design, with only what is needed to burn landfill gas reliably:

  • Combustion chamber in painted carbon steel (stainless steel shroud as an option), with a PID-controlled air louvre and duty/standby temperature probes, and 5:1 turndown.
  • Spark ignition with a pilot burner, and a self-checking UV flame sensor.
  • A gas booster with an ExN motor, direct drive and stainless steel impeller, head of at least 150 mbar, star-delta starter and a condensate knockout pot.
  • A minimal control panel: start and burn only, with shutdown on flame loss. The controls sit behind an internal swing frame, and only an emergency stop is on the door.

Options included a stainless steel shroud and a walk-in acoustic housing, and an orifice plate and manometer for flow readings (later omitted on one hire).

Customer responsibilities

The customer supplied the field gas connection (a DN150 flange), a power supply or generator of suitable size, an earthing arrangement and a compound base, here about 7 m by 4 m.

What to consider for your own project

  1. Decide early whether you might buy. If so, ask for a lease purchase quote at the outset.
  2. Read the extras. Delivery, installation, crane hire and removal can be separate lines.
  3. Check the regulator. Temporary flares at permitted sites still need to meet your permit. See the Environment Agency’s LFTGN05.
  4. Prepare the site. Gas connection, power and a base are usually yours.

FAQ

Can hire fees be deducted from a purchase price?

Not under a pure hire contract, because of how the supplier must account for the asset. A lease purchase is the usual workaround.

How long is a minimum hire period?

Six months in both examples.

What does a hire flare include?

A minimum-specification enclosed flare with booster, knockout pot and basic controls.

Can I hire a smaller flare?

Yes. A solar-powered wellhead flare was also available for hire, covered in our post on a solar-powered wellhead flare.

Need a flare quickly?

Tell us your flow and expected duration and we will advise on hire or purchase.

Start your enquiry :


Translate »
organics.co.uk
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.