Dry cell anaerobic digestion (DCAD) treats solid organic waste without mixing it with water. Waste above 35% dry matter is loaded into sealed concrete cells, recirculated with leachate and digested for around 56 days. A feasibility study for a regional facility planned about 230 tonnes of waste per day, producing biogas for upgrading to bio-CNG and digestate for fertiliser.
The challenge: waste with nowhere to go
In the study area, collected waste exceeded the capacity of the official system by several hundred tonnes a day. The organic fraction is about 65%, mostly market fruit and vegetables and restaurant food waste. Landfilling it emits methane and uses scarce space.
The process
- Reception and pre-treatment. Weighing, inspection, sorting of plastics and metals, shredding and homogenising.
- Screening. Two trommels (80 and 25 mm) before storage or the cells.
- Cell filling. A conveyor fills each cell through trap doors in the roof. Cells are filled in rotation.
- Start-up. Once sealed, leachate is circulated. After 8 days gentle suction begins until extraction matches production.
- Steady gas. Gas is drawn off for 48 days, then the cell is emptied and refilled. Staggering cells gives steady output.
- Gas handling. Each cell can be checked daily. A manifold feeds a dewatering unit that cools gas to a maximum of 80% relative humidity at 40°C.
- Leachate. Reused from active cells, with treatment by alternating aerobic and anaerobic conditions for nitrogen and phosphorus.
Upgrading options
| Method | How it works |
|---|---|
| Membranes | Two stages; second-stage reject (about 25% methane) is recycled to the inlet buffer |
| Water scrubbing | Pressurised water absorbs CO₂, H₂S and contaminants; methane, with low solubility, stays in the gas |
The digestate is separated into solid and liquid fractions for organic fertiliser, or can be converted to refuse-derived fuel or biochar.
Why DCAD suits mixed waste
- No water pre-mixing, so less liquid to treat.
- Tolerant of contamination such as small plastic and wood.
- Modular and batch, so one cell can fail without stopping the plant.
The wider feasibility picture
The study also covered markets (gas, fertiliser, carbon credits), policy, stakeholders, risk and ESG. Those parts depend on local conditions and are not reproduced here.
What to consider
- Secure feedstock agreements.
- Sort at source where possible.
- Plan for odour control.
- Decide on the end markets for gas and digestate.
UK guidance: Anaerobic Digestion Strategy and Action Plan.
FAQ
What is dry matter content?
The proportion of the waste that is not water. DCAD works above 35%.
How long is each batch?
About 56 days (8 days start-up plus 48 days of gas).
What is leachate used for?
Recirculated to start digestion.
Can the gas make electricity?
Yes, in boilers or gas engines.